1. The Challenge:
Center Grove’s goal was clear: reduce rising energy costs and drive district facilities toward net-zero performance—producing as much energy annually as each site consumes.
2. Project Drivers:
- Reduce energy costs and support long-term budget stability
- Drive facilities toward net-zero energy use
- Support a goal of producing as much energy as facilities consume annually
- Enable two schools to become the first net-zero schools in Indiana
- Reduce peak demand by aligning solar production with the hottest part of the day
3. Envocore’s Solution:
Envocore delivered complete solar installations across four sites, including both rooftop and ground-mounted arrays designed to offset each facility’s energy load.
Scope included:
- Complete solar systems including modules, inverters, racking, wiring, and all balance-of-system components
- Integration into existing energy infrastructure for co-located schools and administration buildings
- A unique design powering two separate facilities from one solar array
4. By the Numbers
Total Solar Installed:
- 1.59 MW rooftop solar
- 1.33 MW+ ground-mounted solar
Project Materials:
- 5,259 solar modules
- 6,245 ballast blocks (~74 tons of concrete)
Estimated Annual Production:
- 2,993,320 kWh annual energy saved across all sites
5. Results / Impact
This multi-site solar deployment helps Center Grove advance its energy efficiency and sustainability goals—while positioning key facilities to achieve net-zero energy performance.
6. Testimonial
“Envocore’s team demonstrated a high level of professionalism and reliability throughout the project… What stood out most was the team’s responsiveness and adaptability. They navigated challenges such as change orders and unforeseen delays in a fair, respectful, and expedient manner, always keeping the project’s best interest in focus.”
— Konrad Kutter, Principal, Energy Solutions, CMTA, Inc.