Brief Project Summary:
The project was completed December 5th, 2011 with the replacement of 44 controllers managing over 700 stations/zones and the replacement of over 5,000 sprinkler heads. This project also includes the installation of a weather station, solar powered controllers and multiple system remote controllers and web access based on user classification.
We also completed work on the restrooms and included a rain water harvesting design to be constructed in the future.